Large lock at Ballard Locks drained for yearly maintenance

Posted

The large lock at the Ballard Locks has been drained for yearly maintenance as crews conduct multiple projects over the 18-day closure.

Photo by Abigail Chipps

The U.S. Army Corps of Engineers closed the large lock on Nov. 2, and it will remain closed until Nov. 20. During the closure, crews will:

  • Replace anodes to fight corrosion: The anodes protect the locks’ steel gates, valves, and submerged metal infrastructure from galvanic corrosion.
  • Barnacle scraping to reduce harm to juvenile salmond
  • Miter gate instrumentation: The U.S. Army Engineer Research and Development Center (ERDC) is studying how the horizontally framed miter gates transfer loads.
  • Hydraulic cylinder replacement: Repairing the large lock culvert valve
  • Repairs to concrete

Crews scrape barnacles during the dewatering to protect juvenile salmon. Photo by Abigail Chipps

U.S. Army Corps of Engineers public affairs specialist Abigail Chipps says that in past dewaterings, crews have found a skateboard, cell phones, and rope cleats. They once found a driver’s license and were able to return it to its owner.

While the large lock is closed, pedestrians and bikers can still pass over the locks. The small lock remains open during the large lock closure.

This is the second large lock closure of the year: In February, crews drained the large lock for another shorter maintenance project.

Photos by Abigail Chipps

Ballard